| Client |
|
Ministry
of Water and Environment |
|
|
|
|
Project Duration |
|
2
Years |
|
|
|
|
Consultant |
|
Sana’a
Municipality |
|
|
|
|
Contractor |
|
Al-Rehab
Engineering
|
|
|
|
|
Project Value |
|
$
2,996,000
|
|
|
|
|
Description of Project: |
|
Sewage
Networks, Earth Works and Asphalt
Works. |
|
|
|
|
|
Earth
Work= 140,000 m3 |
|
|
|
|
|
Base
Course=3000m3 |
|
|
|
|
|
Asphalt
works =10,000 m2 |
|
|
|
|
|
Curbstone
= 2,800 m |
|
|
|
|
|
Tile
Works= 1,600m2 |
|
|
|
|
|
47,000mtr
under ground pipes. |
|
|
|
|
|
780
Manholes &
1300 Collection Chambers.
|
|
|