| Client |
|
Ministry
of Youth & Sports
|
|
|
|
|
Project Duration |
|
N/A |
|
|
|
|
Consultant |
|
Ministry
of Youth & Sports
|
|
|
|
|
Contractor |
|
Al-Rehab
Engineering
|
|
|
|
|
Project Value |
|
$
20,750,500
|
|
|
|
|
Description of Project: |
|
Construction
of a Sport Hall building with more
than 45,000cu concrete structure. |
|
|
|
|
|
|
|
25,000m2
floor area. |
|
|
|
|
|
|
|
Sewage
Networks, Mechanical and Electrical
Installations and Pumping Systems. |
|
|
|
|
|
|
|
Earth
Work=175,000m3 |
|
|
|
|
|
|
|
Concrete
Works=45,000m3 |
|
|
|
|
|
|
|
Steel
works= 3800mton |
|
|
|
|
|
|
|
Mechanical
plants, Substations and Electrical
installations. |
|
|
|
|
|
|
|
Pipe
works= 8870mtr |
|
|
|
|
|
|
|
Curb
Stone= 8,000m |
|
|
|
|
|
|
|
Base
Course= 16,000m3 |
|
|
|
|
|
|
|
Asphalt
Works= 80,000m2 |
|
|
|
|
|
|
|
R.C.
Water Tank= 400m3 |
|
|
|
|
|
|
|
Sewage
Water Networks= 4000mtr. |
|
|